ANTICIPATED PAVING ACTIVITIES – (Please refer to map)
• July 13 to July 19: Paving Activities (raising manholes and milling) weather permitting.
• July 13: Paving Stage 1 activities commences.
• July 17: Tack Oil begins at 6 pm.
• July 18: Paving. No vehicle access in red/blue highlighted areas.
• July 19: Paving Stage 2 activities commences. Activity completion.
ANTICIPATED IMPACTS:
• No access to residential parkade for Cambridge Manor, Maple, Esquire, Capella on Tues, July 18 from 7 am to 5 pm.
• East entrance to underground parkade on McCaig St closed Wed, July 19 from 7am to 5pm.
• Intermittent disturbances to back lane south of August west entrance on McLaurin St.
• Strong asphalt odour, increase in noise, limited street parking, temporary road and crosswalk closures, intermittent single lane closures and vehicle access impacts in highlighted areas.
• Temporary access disturbances.
MITIGATIONS:
• Alternative parking is available for all residents on July 17 & 18. o L0t 20 and Lot 21 located west of Save-On-Foods o Block 13 a & b
• Flaggers on site to direct traffic as required. Follow all fresh oil precautionary signage.
Comments